The constriction contract by modernization of runway at the Airport Rostov-on-Don will make a deal with LLC «Transstroymechanizacia». The tender of this organization was admitted by Joint Stock Company “ Rostovaeroinvest” which most fully conform with demands tender documents. There were 3 tenders from Russian companies.
Realization of reconstruction will be from 1 April till 6 June 2015 year. The reconstruction will be doing in 12 hours “gaps” from 8.30 till 20.30 for sustaining flight connection of Rostov Airport by most actual routes. All air companies making flights from the Southern Federal District had had the allocation letters about closing the airport in noted hours.
The contractor LLC «Transstroymechanizacia» must do the installation and construction work, the pre-commissioning activities with purchasing all necessary goods and equipment. In particular it is planning to do reconstruction of runway and strengthening of surface, also to do reconstruction of lighting facilities. For doing all work delivery in time in proximity to runway will be lead up two asphalt concrete factory for maximum operatively work.
After reconstruction the capable surface of runway will be increase and the Airport will have opportunity to take the aircrafts like Boing 737-800, Airbus -320 and another heavy aircrafts.